The cable ship
NIWA arrived at Salalah spares depot on 11-03-2012.
·
Preparations are now
ongoing to load spare cable and jointing kits onto the ship
·
Cable mobilization
for the Mombasa mission is expected on 12-03-2012
·
So far we are still
on schedule (cable ship expected to arrive at Mombasa on 18-03-2012, for 4 day
repair works ending 23-03-2012, all going well)
·
We will continue to update regularly, at least every 48 hours.
·
Once again we thank you for your patience and
understanding as we try our level best to repair the cable and restore full
services asap.
Best Regards……………..?